How much to build a 5-Bedroom Duplex in Lagos

Large family duplex — the aspirational Lagos home. BQ (Boys' Quarters) often included. Commonly found in GRA estates, Lekki Phase 1, Banana Island.

5-bed~320 sqm10-18 months120M–₦200M (standard)

🧱 How much will it cost to build?

Pick a house type, finish level and location — see the cost breakdown by stage.

5-Bedroom Duplex · Standard finish · Mainland
120.0M–₦200.0M
Mid-grade tiles, Dulux paint, stone-coated roofing options · 10-18 months build time
800
Cement (50kg bags)
12 tons
Iron rods
7,000
9-inch blocks
280 sqm
Roofing
Cost breakdown by stage
Foundation
15% of total
12.0M–₦30.0M
Superstructure
18% of total
14.4M–₦36.0M
Decking
12% of total
9.6M–₦24.0M
Roofing
10% of total
8.0M–₦20.0M
Plastering & First Fix
10% of total
8.0M–₦20.0M
Finishing
28% of total
22.4M–₦56.0M
Electrical & Plumbing & Ext
7% of total
5.6M–₦14.0M

Stage-by-stage cost breakdown

Total estimate: 120,000,000–₦200,000,000

Foundation
15% of total
12.0M–₦30.0M
Superstructure
18% of total
14.4M–₦36.0M
Decking
12% of total
9.6M–₦24.0M
Roofing
10% of total
8.0M–₦20.0M
Plastering & First Fix
10% of total
8.0M–₦20.0M
Finishing
28% of total
22.4M–₦56.0M
Electrical & Plumbing & Ext
7% of total
5.6M–₦14.0M

Labor rates for this build

All construction artisans you'll need for this project

RoleDaily rateMonthly rate
Bricklayer/Mason
Lays blocks, renders walls. The most critical artisan — bad bricklaying means uneven walls and structural issues. Experienced bricklayers charge premium.
5,000–₦10,000120,000–₦250,000
Carpenter
Roofing framework, formwork for concrete casting, doors/window frames. A good roofing carpenter prevents leaks for decades.
5,000–₦8,000100,000–₦200,000
Plumber
Water supply and drainage installation. First fix (before plastering) and second fix (after tiling). Poor plumbing causes the most expensive post-construction repairs.
4,000–₦8,00080,000–₦180,000
Electrician
Wiring, conduit installation, panel board, earthing. MUST be certified — unlicensed electricians cause house fires. First fix and second fix stages.
4,000–₦8,00080,000–₦180,000
Tiler
Floor and wall tile installation. Specialist tilers (marble, porcelain) charge N10K-N18K/day vs N5K-N8K for standard ceramic.
5,000–₦12,000100,000–₦250,000
Painter
Interior and exterior painting. Screeding, filling, undercoat, and finishing. A 3-bedroom needs 2-3 weeks of painting work.
4,000–₦7,00080,000–₦150,000
POP Installer
Plaster of Paris ceiling specialist. Paid per sqm (N3K-N6K/sqm installed) rather than daily rate. Cornices and decorative work cost extra.
5,000–₦10,000
Welder/Iron Bender
Bends and ties iron rods for reinforcement. Also fabricates gates, burglar-proof bars, and railings.
4,000–₦8,00080,000–₦160,000
Laborer (General)
Carries materials, mixes mortar, assists artisans. A site needs 3-6 laborers depending on project size.
3,000–₦5,00060,000–₦100,000
Site Engineer/Foreman
Supervises construction, reads drawings, manages artisans. A qualified site engineer prevents costly structural mistakes. 5-7% of project budget.
15,000–₦30,000350,000–₦600,000

📝 The Lagos context

Five-bedroom duplex na the premium end of the private-home market for Lagos — two-storey house, usually with ensuite master, several other bedroom, generous living and dining space, and often BQ, wey dem site for the estate of Lekki, Ikoyi, Ikeja GRA and the newer development. As storey building e dey carry cost wey bungalow no get: suspended floor slab, staircase, more structural steel and bigger roof, all of wey dey push both the material bill and the engineering up.

Finish level na where the range really open. For standard finish five-bed duplex na already substantial build; for luxury finish — imported tile, fitted kitchen, smart-home wiring, quality joinery, elaborate POP and premium sanitaryware — the finishing fit rival the cost of the structure itself. Material price dey set the shell, but for this size and spec the finishing and the services (plumbing, electrical, sometimes lift or generator house) na big line for their own right. Land, wey no dey here, typically na premium too.

For build of this scale, professional input dey pay for itself. Proper structural design, competent builder and close cost control matter far more than dem dey do for bungalow, because the sum bigger and the mistake more expensive. To bulk-buy structural material still dey help, but the bigger lever na sound design, disciplined finishing spec, and supervision wey dey keep long, complex project on budget from foundation to handover.