How much to build a 2-Bedroom Bungalow in Lagos

The most affordable building option for small families. Simple rectangular design reduces cost. Best value in areas like Epe, Ikorodu, Ibeju-Lekki where land is cheap.

2-bed~100 sqm4-6 months25M–₦35M (standard)

🧱 How much will it cost to build?

Pick a house type, finish level and location — see the cost breakdown by stage.

2-Bedroom Bungalow · Standard finish · Mainland
25.0M–₦35.0M
Mid-grade tiles, Dulux paint, stone-coated roofing options · 4-6 months build time
250
Cement (50kg bags)
2.5 tons
Iron rods
2,000
9-inch blocks
120 sqm
Roofing
Cost breakdown by stage
Foundation & Substructure
20% of total
3.6M–₦7.0M
Block Work & Superstructure
25% of total
4.5M–₦8.8M
Roofing
12% of total
2.2M–₦4.2M
Plastering & First Fix
10% of total
1.8M–₦3.5M
Finishing (tiles, paint, doors, windows)
25% of total
4.5M–₦8.8M
Electrical & Plumbing
8% of total
1.4M–₦2.8M

Stage-by-stage cost breakdown

Total estimate: 25,000,000–₦35,000,000

Foundation & Substructure
20% of total
3.6M–₦7.0M
Block Work & Superstructure
25% of total
4.5M–₦8.8M
Roofing
12% of total
2.2M–₦4.2M
Plastering & First Fix
10% of total
1.8M–₦3.5M
Finishing (tiles, paint, doors, windows)
25% of total
4.5M–₦8.8M
Electrical & Plumbing
8% of total
1.4M–₦2.8M

Labor rates for this build

All construction artisans you'll need for this project

RoleDaily rateMonthly rate
Bricklayer/Mason
Lays blocks, renders walls. The most critical artisan — bad bricklaying means uneven walls and structural issues. Experienced bricklayers charge premium.
5,000–₦10,000120,000–₦250,000
Carpenter
Roofing framework, formwork for concrete casting, doors/window frames. A good roofing carpenter prevents leaks for decades.
5,000–₦8,000100,000–₦200,000
Plumber
Water supply and drainage installation. First fix (before plastering) and second fix (after tiling). Poor plumbing causes the most expensive post-construction repairs.
4,000–₦8,00080,000–₦180,000
Electrician
Wiring, conduit installation, panel board, earthing. MUST be certified — unlicensed electricians cause house fires. First fix and second fix stages.
4,000–₦8,00080,000–₦180,000
Tiler
Floor and wall tile installation. Specialist tilers (marble, porcelain) charge N10K-N18K/day vs N5K-N8K for standard ceramic.
5,000–₦12,000100,000–₦250,000
Painter
Interior and exterior painting. Screeding, filling, undercoat, and finishing. A 3-bedroom needs 2-3 weeks of painting work.
4,000–₦7,00080,000–₦150,000
POP Installer
Plaster of Paris ceiling specialist. Paid per sqm (N3K-N6K/sqm installed) rather than daily rate. Cornices and decorative work cost extra.
5,000–₦10,000
Welder/Iron Bender
Bends and ties iron rods for reinforcement. Also fabricates gates, burglar-proof bars, and railings.
4,000–₦8,00080,000–₦160,000
Laborer (General)
Carries materials, mixes mortar, assists artisans. A site needs 3-6 laborers depending on project size.
3,000–₦5,00060,000–₦100,000
Site Engineer/Foreman
Supervises construction, reads drawings, manages artisans. A qualified site engineer prevents costly structural mistakes. 5-7% of project budget.
15,000–₦30,000350,000–₦600,000